40 men can build a wall 4 metres high in 15 days the number of men required to bulid a samilar wall 5 metres high in 6 days
Answers
Answered by
8
Answer:
40 men ,4 meter wall=15 days
Therefore,1 meter wall=40÷4=10 men
Therefore,5 meter wall=10×5=50 men
50 men 5 meter wall =15 days
1 day=50×15=750 men
6 day = 750÷6=125 men
Answered by
0
The number of men would be 125.
Step-by-step explanation:
Since we have given that
Number of men = 40
Length of wall = 4 meter
Number of days = 15
If the length of wall = 5 meter
and number of days = 6
Then, we need to find the number of men:
So, Using "Time and work" we get that
Hence, the number of men would be 125.