Math, asked by CorradinoPapa8025, 16 days ago

40 men can build a well 4 metres high in 15 days . The number of men required to build a similar wall 5 metres high in 6 days is

Answers

Answered by anshvadgama06
0
50 men needed and for 5 meters in 6 days
Answered by kiethnathanielsalaza
0

40 men can build 20m high wall in 15 days

=> 1 men can build 20m high wall in 15*40 days

=> 1 men can build 1m high wall in 15*40/20 i.e. 30 days

=> 30 days 1m high wall requires 1 men

=> 30 days 50m high wall requires 1*50 men

=> 3 days 50m high wall required 1*50*10 men

Answer:

500 Men required