. 40 men can catch 200 sharks in 20 days working 6 hours a day. In how many days 25 men can catch 300 sharks working 4 hours a day? a. 30 B. 24
C. 34
D. 20
Answers
25 men can catch 300 sharks in 72 days working 4 hours a day .
Step-by-step explanation:
Given as :
40 men can catch 200 sharks in 20 days working 6 hours a day .
Let 25 men can catch 300 sharks in x days working 4 hours a day
According to question
= constant
Or, =
Or, =
Solving the numerator denominator both side
i.e 24 =
∴ x = 24 × 3
Or, x = 72
So, 25 men can catch 300 sharks in 72 days working 4 hours a day
Hence, 25 men can catch 300 sharks in 72 days working 4 hours a day . Answer
72 days.
Step-by-step explanation:
Given that, 40 men can catch 200 sharks in 20 days working 6 hours a day.
So, 40 men can catch 200 sharks working (20 × 6) = 120 hours.
Then, 1 man can catch 200 sharks working (120 × 40) = 4800 hours.
Or, 1 man can catch 1 shark working (4800 ÷ 200) = 24 hours.
Or, 25 men can catch 300 sharks working (24 × 300) ÷ 25 = 288 hours.
Therefore, if 25 men work 4 hours a day, then the number of days required to catch 300 sharks in (288 ÷ 4) = 72 days. (Answer)