40 men can complete a work in 40 days . they started the work together
but at the end of every 10th day , 5 men left the job. the work would have
been completed in
Anonymous:
they will complete the work in 65.66 days
Answers
Answered by
6
40 men can complete a work in 40 days . they started the work together
but at the end of every 10th day , 5 men left the job. the work would have
been completed in
Solution:
Let the forty man work x hours a day .
Therefore total number of working hours required to complete the work = Number of men *number of days to complete to work * Number of Working Hours (per day
= 40*40*x
= 1600x
hence the Number of Days it will take to complete the same work by the men = 40*10*x + (40 - 5 )*10 *x + (35 - 5 )*10*x + (30 -5)*10*x + (25 -5)*10*x + (20 - 5)*6.66*x
= 400x + 350 x + 300 x + 250x + 200x + 100 x
= 1600x
hence the Number of days = 10 + 10 + 10 + 10 +10 +6.66
=56.66 days
but at the end of every 10th day , 5 men left the job. the work would have
been completed in
Solution:
Let the forty man work x hours a day .
Therefore total number of working hours required to complete the work = Number of men *number of days to complete to work * Number of Working Hours (per day
= 40*40*x
= 1600x
hence the Number of Days it will take to complete the same work by the men = 40*10*x + (40 - 5 )*10 *x + (35 - 5 )*10*x + (30 -5)*10*x + (25 -5)*10*x + (20 - 5)*6.66*x
= 400x + 350 x + 300 x + 250x + 200x + 100 x
= 1600x
hence the Number of days = 10 + 10 + 10 + 10 +10 +6.66
=56.66 days