Math, asked by aman27271, 6 months ago

40 men can cut 60 trees in 8 hours. If 8 men leave the job, how many trees will be cut in 12 hours?
TIME AND WORK
n the previous section, we have studied that the number of men to complete a work and time taken van​

Answers

Answered by Yebin
2

Step-by-step explanation:

32 men can cut in 12 hours 60×32×12/(40×8)=72 trees.

Similar questions