Math, asked by vsanil3807, 11 months ago

40 men can finish a piece of work in 26 days. How many men who be needed to finish it in 16 days?

Answers

Answered by RvChaudharY50
0

Answer:

Total work = (40*26)

To finish in 16 days he need = 40*26/16 = 65 men

[ mark as brainlist]

Answered by mohd2564
0

Hope you are understand.