40 men can finish a piece of work in 26 days How many men will be needed to finish it in 65 days
Answers
Answered by
1
Step-by-step explanation:
Number of men needed to complete the work in 26 days = 40 men
Number of men needed to complete the work in 1 day =(40×26) = 1040
Number of men needed to complete the work in 65 days = 1040/65 = 16
THANKS