40 men can finish a piece of work in 26 days How many men will be needed to finish it in 65 days​

Answers

Answered by arvindmishra9929
1

Step-by-step explanation:

Number of men needed to complete the work in 26 days = 40 men

Number of men needed to complete the work in 1 day =(40×26) = 1040

Number of men needed to complete the work in 65 days = 1040/65 = 16