40 men can finish a piece of work in 26 days. How many men will be needed to finish it in
16 days?
Answers
Answered by
1
Answer:
32men
Step-by-step explanation:
26days = 40 men
16 days = ?
= 40× 16 / 20
= 32
so, 32 men will be needed to finish the work in 16 days
navyasharma0308:
thank you so much
Answered by
0
Answer:
24 mens
Step-by-step explanation:
40 mens can do in 26 days ∴ in 26 days 40 mens can do the work
∴ in 1 days 40÷ 26 mens can do the work . ∴ in 16 days(40÷26×16) = 24 mens