40 men can finish a piece of work in 26 days . how many men will be needed to finish it in 16 days.
Answers
Answered by
66
hello ☺
40 men can do the work in 26 days.
Total man days required for the work =
40X26
=1040 days.
To finish it in 16 days the number of men required
= 1040/16
=65 men.
so we can say that 65 men can do the work in 16 days.
thank you
40 men can do the work in 26 days.
Total man days required for the work =
40X26
=1040 days.
To finish it in 16 days the number of men required
= 1040/16
=65 men.
so we can say that 65 men can do the work in 16 days.
thank you
Answered by
0
Answer:
the answer is 65 for 16 days
Similar questions