Math, asked by jitendraverma69, 1 year ago

40 men can finish a piece of work in 26 days . how many men will be needed to finish it in 16 days.

Answers

Answered by NidhraNair
66
hello ☺

40 men can do the work in 26 days.

Total man days required for the work =
40X26
=1040 days.

To finish it in 16 days the number of men required
= 1040/16
=65 men.

so we can say that 65 men can do the work in 16 days.

thank you
Answered by sunakarbehera1981
0

Answer:

the answer is 65 for 16 days