Math, asked by reenatripathi53, 11 months ago

40 men can finish a piece of work in 26 days how many men will be needed to finished it in 16 days

Answers

Answered by aaryansh00
24

40 men can do the work in 26 days.


Total man days required for the work = 40*26=1040 man days.


To finish it in 16 days the number of men required = 1040/16=65 men.


65 men can do the work in 16 days.


aaryansh00: If u like the answer mark as brainly
reenatripathi53: thank you very much
aaryansh00: Wlcm nice profile pic too...
aaryansh00: Mark as brainly
reenatripathi53: thank
aaryansh00: But put your profile pic
reenatripathi53: means
aaryansh00: Accept friend req
Answered by mamun59
11
26 days is required for 40 mens
In 1 days mens are required = 40× 26
For 16 days, the required mens are = 40×26/16= 65

Hope this will help you
Similar questions