40 men can finish a piece of work in 5 days then what time can 50 men do the same work?

Answers

Answered by goyalb668
1

Step-by-step explanation:

40 men can finish a work = 5 days

one man can finish work = 5/40 days

men men can finish work = 5/40 X 50

= 25/4 days

Answered by nakulanoop
1

Answer:

in 4 days

Step-by-step explanation:

40 men  in 5 days

one days work of 40 men =1/5

one days work of 1 man=1/(5*40)

one days work of 50 men=(1*50)/200=1/4

50 men can therefore finish it in 4 days