40 men can inish a piece of work in 26 days. How many men will be needed to finish it in
16 days?
Answers
Answered by
19
Answer:
M1 * D1 = M2 * D2
40 * 26 = X * 16
X = 40*26/16 = 65 men (Ans)
(Mark as brainlist)
Answered by
5
Step-by-step explanation:
40 men = 26 days
x = 16 days
So...40×26÷16
=65 days