40 men planned to complete a certain work in 20
days working 6 hours per days. After 15 days only
3/5 th of the work was completed, how many extra
men required to complete the work on time working
8 hours per day ?
Answers
Answered by
0
Given :
40 men planned to complete a certain work in 20 days working 6 hours per days.
After 15 days only of the work was completed
To Find :
The number of extra men required to complete the work on time working 8 hours per day
Solution :
Let The number of extra men = x
We know,
= constant
The number of men = = 40
The number of days = = 15
The number of hours = = 6 per days
Work done = =
Again
The number of men = = ( 40 + x )
The number of days = = 5
The number of hours = = 8 per days
Work done = = 1 - =
So, =
Or, =
or, =
Or, 40 × 5 × 6 = ( 40 + x ) × 5 × 4
Or, 1200 = 800 + 20 x
Or, 20 x = 1200 - 800
Or, 20 x = 400
∴ x =
i.e x = 20
So, number of extra men = 20
Hence, The number of extra men required to complete the work on time working 8 hours per day is 20 . Answer
Similar questions
English,
5 months ago
Physics,
5 months ago
English,
5 months ago
English,
10 months ago
Computer Science,
10 months ago