Math, asked by juniwalvinita, 5 hours ago

40 persons take 25 days to complete the work. How long will it take to complete the

same if 10 more persons join them?​

Answers

Answered by sathvikchatterji
1

50 workers 20 days

p = 40

d = 25

40 + 10 = 50

50 × 10 ÷ 25

= 20 (ans)