40 workers can complete a 100m long road repairing job in 50 days. In order to complete the same task in 40 days, how many additional workers required?
Answers
Answered by
2
Hence 32 additional workers will be needed to complete the same road in 40 days.
Attachments:

harshkantchandanshiv:
this is wrong