Math, asked by sharmamonica697, 7 months ago

40 workers can complete a piece of work in 36 days how many workers will be required to finish the work in 15 days​

Answers

Answered by ManisaMeher
7

Answer:

96

Hope it will help you

Answered by Anonymous
11

\bigstar\huge\mathbf\red{Answer}

In 36 days the number of workers who can complete a piece of work are :- 40 workers

In 1 day the number of workers can complete a piece of work are :- 40 × 36 workers

In 15 days the number of workers can complete a piece of work are :- ( 40 × 36 ) / 15

= 3 × 12 = 36 workers