40 workers can make 16 shelves in 8 days. How many days will workers take to make 24 shelves.
Answers
Answered by
0
Answer:
12
Step-by-step explanation:
M1×D1 = M2×D2
W1. W2
40×8 = 40×x
16 24
20 = 10×x
6
12=x