Math, asked by sounavbiswas1, 8 months ago

40 workmen agreed to dig a pond in 56 days. They started by working 6 hours a day, but 9 after 36 days 16 workmen fell ill. It was found that th part of the work had been done. 13 how many hrs a day did the remaining men work to finish the work in time?

Answers

Answered by harshit3535
0

Answer:

Step-by-step explanation:

◆ Answer -

(a) No of days = 5 days

(b) No of workers = 24 days

● Explanation -

We'll first calculate work hours by 1 person to dig 1 pit.

Work hours = 40 × 10 × 6 / 30

Work hours = 80 hrs

Thus, One person will take 80 hours to dig one pit.

(a) For condition A -

No of days = 80 × 15 / (20 × 12)

No of days = 5 days

(b) For condition B -

No of workers = 80 × 6 / (4 × 5)

No of workers = 24 days

Thanks dear...