400 persons, working 9 hrs per day complete 1/4th of the work in 10 days. The number of additional persons, working 8 hrs per day, required to complete the remaining work in 20 days, is:
Answers
let number of workers completing the work in 20 days be as x
work done = 1/4
remaining work = 1- 1/4 = 3/4
hours per day 8:9
work 1/4 :3/4
days 20:10::400:x
8 x 1/4 x 20 x X=9 x 3/4 x 10 x 100
40x = 27000
x = 675
additional men = 675-400 =275
CONCEPT:
the concept used here is the concept of ratio.
TOTAL WORK=( no of person*hours worked*days need to complete)/work completed or wage got.
we should equalise the ratio before and after the change in workers, hours etc and find the variable
GIVEN:
total no of persons before addition=400
time required by 400 persons to complete 1/4 th of work=9 hours.
completed work=1/4th
FIND:
Number of persons working 8 hours per day required to complete the remaining work in 20 days;
SOLUTION:
let the number of people completing the work in 20 days=x.
remaining work=3/4 th part of work.
ratio of hours per day now and then(before addition of workers and after addition of workers)=8:9
ratio of work now and then(before addition of workers and after addition of workers)=1/4:3/4
days now and then(before addition of workers and after addition of workers)=20:10
persons required now and then(before addition of workers and after addition of workers)=x:400
so in whole lets make the ratio.
8*1/4*20*x=9*3/4*10*400
40x=27000
x=675
so the number of total workers is 675
so the number of additional workers=675-400=275
so the number of additional persons, working 8 hrs per day, required to complete the remaining work in 20 days, is 275
#SPJ3