40men can finish a peice of work in 26 days how many mam will needed to finish the same work in 16 days
Answers
Answered by
5
hiii,
26-----40
16-------x
26/16 = x/40
=>16x = 40 × 26
=> x = 40 × 26/16 = 65
hope helps
26-----40
16-------x
26/16 = x/40
=>16x = 40 × 26
=> x = 40 × 26/16 = 65