Math, asked by banerjees792, 1 year ago



41. A takes 5 days more than B to do a certain job and 9 days more than C; A and B together can do the
job in the same time as C. How many days A would take to do it?​

Answers

Answered by yash141741
0

Answer:

ten days a would take to do