42. A takes 5 days more than B to do a certain job and 9
days more than C; A and B together can do the job in
the same time as C. How many days A would take to
do it?
(a) 16 days
(b) 10 days
(c) 15 days
(d) 20 days
Answers
Answered by
21
Answer:
15 days
Explanation:
let total work =1
time taken by A=t
time taken by B=t–5
time taken by C=t–9
Given