42. A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can
finish it in 4 days, find the time taken by B to finish the work.
Answers
Answered by
0
Answer:
12/5
Step-by-step explanation:
first a and b 1 day work=1/6-1/4=5/12.. mereko nahi aata sorry
Answered by
0
1/x-6+1/x=4
x+x-6/4x-24=4
2x-6=16x-96
14x=90
x=14/90