420 men can complete construction of a building in 9 months . Due to request by owner of the job was completed in 7 months by employing some more men . find how many more are employed
Answers
Answered by
1
Answer:
I am following you
Step-by-step explanation:
Men Time
420 9 months
x 7 months
As the number of workers is inversely proportional to time taken:
420×9=x×7⟹x=7420×9=540
∴ extra men needed: 540−420=120
Answered by
2
Men Time
420 9 months
x 7 months
As the number of workers is inversely proportional to time taken:
420×9=x×7⟹x=7420×9=540
∴ extra men needed: 540−420=120
Similar questions