Math, asked by sandhyasinha2303, 2 months ago


44 men can finish a piece of work in 36 days.
How many men will be needed to finish it in
16 days?
(tell me the easiest way to solve)​

Answers

Answered by mk8471139
2

Answer:

99

Step-by-step explanation:

Bro, it is an indirect variation

So, the answer is

 \frac{no. \: of \: men \:  \times no. \: of \: days \: }{required \: no. \: of \: days} \\  =  \frac{44 \times 36}{16}  = 99

Hence 99 men can complete the work in 16 days