44 men can finish a piece of work in 36 days. How many men will be needed to finish it in 10days?
Answers
Answered by
0
Answer:
12.222
Step-by-step explanation:
a piece of work in 1 days = 44/36 = 1.222
men will be needed to finish it in 10days = 1.222x10
= 12.222
Answered by
0
Answer:
12.222
Step-by-step explanation:
a piece of work in 1 days = 44/36 = 1.222
men will be needed to finish it in 10days = 1.222x10 = 12.222