45. 10 men can dig a pit in 29 days. If a man works
half as much as a boy, then 5 men and 12 boys
can dig it in
(A) 10 days
(B) 15 days
(C) 12 days
(D) 14 days
Answers
Answered by
159
=> Answer => Option - (A)
To calculate the word done by them at first we have to find out word by a man and boys then calculate work by 5 men and 12 boys.
Now calculate work done by 5 men and 12 boys:-
Answered by
37
Step-by-step explanation:
Given That :-
Total Work Done = 29 day * 10 men = 290
10M = 29 days
B = 2 M
So Acc. to Question ⁉️
= > 5 M + 12 B = 290 ( Total Work )
= > 5 M + 12 * 2 M = 290
= > 29 M = 290
M = 10 days ✅