Math, asked by pratikgamer521, 6 hours ago

45 labours finish the work in 27 days. How many labouress will complete the

same work in 15 days ?​

Answers

Answered by goelmridul03
2

Answer:

answer is 81

Step-by-step explanation:

refer attachment for explanation

pls mark me brainliest