45 men can dig a tunnel in 28 days how many more men will be needed to dig in 18 days.
ans 25 this belongs to direct and inverse variation please step by step explanation
Answers
Answered by
0
Step-by-step explanation:
48 men can dig a trench in 14 days
1 man can dig a trench in =(14×48) days .. [ less men, more days]
∴28 men can dig a similar trench in =(14×48)/28
=24 days ...[ More men, less days]
Hence, the required number of days for 28 men to dig a trench =24.