45 men or 60 boys can do a piece of work in 20 days. how many days will 15 men and 20 boys take to complete the work?
Answers
HELLO DEAR,
YOUR QUESTIONS IS-------------->45 men or 60 boys can do a piece of work in 20 days. how many days will 15 men and 20 boys take to complete the work?
FOR MEN -
45 men complete work in 20 days
So 45 men one day work= 1/20
1 men one day work = 1/20×45
FOR BOYS
60 boys complete work in 20 days
So 60 boys one day work= 1/20
1 boys one day work = 1/20×60
Now we have to find when both (15 Men & 20 boys) are working togethers
So 15 Men one day work = 15 × (one day work of one man)
= 15 × (1 / 20 × 45) =1/60
So 20 boys one day work = 20 × (one day work of one boys)
= 20 × (1 / 20×60) =1/60
Adding one day work of (15 Men) & (20 boys)
= 1/60 + 1/60
= 2/60
= 1/30
This means 15 Men and 20 boys does 1/30 fraction of work in one day
Thus, they would complete the work in
30 days.
I HOPE ITS HELP YOU DEAR,
THANKS
Given 45 men or 60 boys.
Then, 1 men = (60/45) = 4/3 boys.
= > 15 men = (4/3) * 15 = 20 boys.
So,
Total boys = 20 + 20 = 40
Now,
Given 60 boys can do a work in 20 days.
Then, 40 boys can do the same work in (20 * 60)/40 = 30.
Therefore, 15 men and 20 boys can complete the work in 30 days.
Hope this helps!