46. 6. The rates of working of A and B are in the
ratio 3:4. The number of days taken by them to
finish the work are in the ratio
(a) 3:4
(b) 9:16
(c) 4:3
(d) 16:9
Answers
Answered by
3
Answer:
We know that the number days taken to work is the reciprocal of the rate of the work i.e they are inversely proportional.
So, we calculate the work done by A=1/3
And the work done by B=
4
1
∴ ratio of the work done =
3
1
:
4
1
i.e. 4:3
Answered by
27
Step-by-step explanation:
✳Question✳
✳The rates of working of A and B are in the ratio 3:4 The number of days taken by them to finish the work are in the ratio✳
✳Answer✳
✳(b)4:3✳