47. A, B and C can do a piece of work in 10, 12 and 15 days respectively. They work
together for some days. But A leaves 5 days before the completion of the work and B
leaves 2 days after A. How long does the whole work last​

Answers

Answered by gkavi53
0

Answer:

They work more than 10 days