Math, asked by suriya777, 3 months ago


47. A can finish a piece of work in 48 days. He worked alone for 18 days and then B

joined him. Together they could finish the remaining work in 18 3/4 days. In how
many days can B alone finish the same piece of work ?
1) 90
2) 60
3) 75
4) 80
5) ​

Answers

Answered by bommaganiakhil45
1

A-48

A+B - 30

so TW =240

B - efficiency 3

B alone= 240/3 = 80

Attachments:
Answered by anirudhayadav393
0

Concept Introduction: Basic arithmetic is the basic concept of Mathematics.

Given:

We have been Given: A alone can finish in

48 \: days

he worked for

18 \: days

and then B joined him. Both finished the remaining work in

18 \times \frac{3}{4}  =  \frac{75}{4}

To Find:

We have to Find: In how many days B can finish the work alone?

Solution:

According to the Problem, A works

 \frac{18}{48}  =  \frac{3}{8}

remaining,

1 -  \frac{3}{8}  =  \frac{5}{8}

therefore, next

 \frac{5}{8}  =  \frac{75}{4}  \\  \frac{5 \times 4}{8 \times 75}  =  \frac{1}{30}

therefore,

240 \div 30 = 80 \: days

Final Answer: B alone can finish the work in

80 \: days