48 men are employed to construct a building in 75 days due to some reason they wanted the building to be ready in 60 days how many men should be employed to construct building in 60 days
Answers
Answered by
2
Answer:
60 men
Step-by-step explanation:
48 * (75/60) = 60
Answered by
7
I hope it will help u