480 men working 9 hours a day can construct a road in 20 days how long would it take to construct the same road if 300 men work 6 hours a day on it
simran658824:
please answer fast
Answers
Answered by
1
equation will be
9/480×20=6/300×X
- 9/24=6/300×X
-9×300/24×6=X
-X=37.5
9/480×20=6/300×X
- 9/24=6/300×X
-9×300/24×6=X
-X=37.5