49 workers a can complete a piece of work in 32days how many workers should be removed to finish the same in 64 days
Answers
Answered by
1
☯️ Heya mate!!! your question was a tricky one but here you go with the answer
time taken by 49 workers = 32 day
number of workers removed for 64 days = ?
this is in inverse proption so,
49 × 32 = 64 × x
= x = 64 × 32 / 49
= x = 41.79
= so, let's take 42 people in place of 41.79
42 people are required
NOTE - we need to find people that should be removed so,
49 - 42 = 7
so, 7 people should be removed
♔ have a great day ahead mate!!!