Math, asked by adityaraj99975, 9 months ago

4men can do a piece of work in 5days how many men will do it in 4days​

Answers

Answered by REDPLANET
0

Answer:

     Men                                       Time taken to complete work                    

 

        4                                                        5 days

        x                                                        4 days

∴ 4  =  {\bold{\frac{5x}{4}}

∴ x =  {\bold{\frac{4\times4}{5}}

∴ x = 3.2 men