4men required 7hours repair a road .How many men requir to repair a road in 2 hours
Answers
Answered by
4
it's inversely proportional so,
4×7=2×y
28/2=y
y=14 men
4×7=2×y
28/2=y
y=14 men
Answered by
0
4*7=2*X
X=14
need 14 men to complete
X=14
need 14 men to complete