5. A and B can complete a work in 12 days. B and C can complete the same work in 18 days. C and A can complete in 24 days. How many days will take for A, B and C combined together to complete the same amount of work?
Answers
Answered by
1
Answer:
Let's take LCM of days
36 is the LCM. Assume the work to be 36 units.
A & B complete 36 units of work in 18 days.
In 1 day, A + B = 2
Similarly, A + C = 3
Similarly, B + C = 4
Adding all,
2A + 2B + 2C = 9
A + B + C = 4.5
But A + C = 3
Hence, B = 1.5
Total work = 36
B will take (36/1.5) = 24 days
Step-by-step explanation:
Hope this helps you please try to Mark me as brainlists please