5. A and B can complete a work in 12 days. B and C can complete the same work in 18 days. C and A can complete in 24 days. How many days will take for A, B and C combined together to complete the same amount of work? in 20 days. If both of them work
Answers
Answer:
A and B can do some work in 12 days, B and C in 15 days & C and A in 20 days. If A, B and C are together, how many days will it take to complete?
It is given that
A and B can do a piece of work in 12 days.
In 1 day, (A+B) can do 1/12th of the work.
B and C can do a piece of work in 15 days.
In 1 day, (B+C) can do 1/15th of the work.
A and C can do a piece of work in 20 days.
In 1 day, (A+C) can do 1/20th of the work.
Now, if we add on the work done by (A+B), (B+C) and (A+C), we will get the work done by (A+B+C) collectively in 1 day.
Therefore,
(A+B) + (B+C) + (A+C) = 1/12 + 1/15 + 1/20
2 (A+B+C) = 12/60
On simplification, we get
(A+B+C) = 1/10
It means that,
In 1 day, (A+B+C) together can do 1/10th of the work.
So, to complete one piece of work together, it will take 10 days.
Hope, it helps!