5. A bridge can be constructed by 1800 workers in 50 days. how many more such workers should be employed to complete the work in 30 days
Answers
Answered by
2
Step-by-step explanation:
1500people————60days
X—————————40days
X(60)=40*1500
X=(40*1500)/60
X=(4*1500)/6
X=1000
Therefore 1000 people required for the completion of work in 40 days