Math, asked by stargenius, 3 months ago

5. A can complete a work in 10 days while B can do it in 15 days. If A and B worked for 3 days and then B left it, find the number of days that A will take to complete the remaining work. give explanation, answer is 5 days​

Answers

Answered by kartheekpeddireddy97
0

Step-by-step explanation:

15-10=5 days

A man can complete in 5 days

thats all mu boy