5. A can do a piece of work in 10 days. He works at it for 4 days and then B finishes it in 9 days. In how many days can A and B together finish the work?​

Answers

Answered by snehafeb96
0

Answer:

"6 days"

Step-by-step explanation:

6 days Explanation: 4/10 + 9/x = 1 => x = 15 Then both can do in 1/10 + 1/15 = 1/6 => 6 days