Math, asked by danishzehendz01, 7 months ago

5
.
A can do a piece of work in 16 days, B in 10 days. A and
B work at it together for 6 days and then C finishes it in
3 days, in how many days could have done it alone? koii answer dedo bhai ​

Answers

Answered by akshatson123
1

Answer:

8 is the right Answer

First Take any work be x

and 2nd be y

and put the values