Math, asked by tamnnatdlgmailcom, 4 months ago


5. A can do a piece of work in 40 days. He works at it for 8 days and then B finishes the
remaining work in 16 days. How long will they take to complete the work if they do it
together?

Answers

Answered by vermaanshika892
6

Answer:

40/3 or 13(1/3)

Step-by-step explanation:

work done by A in 1 day = 1/40

work done by A in 8 days = 1/40*5

= 1/5

The remaining part = 1-1/5

= 4/5

No. of days taken by Y to finish 4/5 part = 16 days

part of work done by Y in 1 day = (4/5)/16

= (4/5)(1/16)

= 1/20

If they work together = 1/40+1/20

= 3/40

So,

the no. days taken by both to complete the work =1/(3/40)

=40/3

or

13(1/3)

Answered by Anonymous
5

Answer:

Answer:

40/3 or 13(1/3)

Step-by-step explanation:

work done by A in 1 day = 1/40

work done by A in 8 days = 1/40*5

= 1/5

The remaining part = 1-1/5

= 4/5

No. of days taken by Y to finish 4/5 part = 16 days

part of work done by Y in 1 day = (4/5)/16

= (4/5)(1/16)

= 1/20

If they work together = 1/40+1/20

= 3/40

So,

the no. days taken by both to complete the work =1/(3/40)

=40/3

or

13(1/3)

Similar questions