5. A can do a piece of work in 40 days. He works at it for 8 days and then B finishes the remaining work in 16 days. How long will they take to complete the work they do it together?
Answers
Answered by
2
A can do a piece of work in =40 days
So, A’s 1 day's work =
40
1
So, A’s 8 day's work =
40
8
=
5
1
∴ Remaining work =1−
5
1
=
5
4
Now, B can do
5
4
piece of work in =16 days
So, B’s 1 day's work =
16
(4/5)
=
5×16
4
=
20
1
Therefore, (A+B)’s 1 day's work =
40
1
+
20
1
=
40
1+2
=
40
3
∴ Both (A+B) can do a piece of work in =
(3/40)
1
days
=
3
40
days
=13
3
1
days
So, A’s 1 day's work =
40
1
So, A’s 8 day's work =
40
8
=
5
1
∴ Remaining work =1−
5
1
=
5
4
Now, B can do
5
4
piece of work in =16 days
So, B’s 1 day's work =
16
(4/5)
=
5×16
4
=
20
1
Therefore, (A+B)’s 1 day's work =
40
1
+
20
1
=
40
1+2
=
40
3
∴ Both (A+B) can do a piece of work in =
(3/40)
1
days
=
3
40
days
=13
3
1
days