5.
A contractor undertook to make 60 km of roadways in 80 days. In 20 days, only 12 km of road was
completed by 360 men working 8 hours a day. The men then agreed to work an hour per day overtime
and some boys were also engaged to assist them and thus
the work was completed in agreed time. Find
the number of boys engaged to assist if the working capacity of 3 boys was equal to that of 2 men.
Answers
3 km road can be made by working (10*24*8)hrs by 180 men
1km............................................................................... 180/3 men
1km.....................................................1 hr...................{180*(10*24*8)}/3 men
12km.............................................................................{180*(10*24*8)*12}/3men
12km...................................................(30*24*9)hrs....{180*(10*24*8)*12}/{3*(30*24*9)}men
=640/3 men
extra men needed=640/3-180=100/3 men
now,
2 men=3 boys
1men=3/2 boys
100/3men=(3/2)*100/3 boys
=50 boys(answer)
it is the example
you see and slove your questions own
I hope it will help you
plz follow me
mark in brain list
60 km = 80 days
12 km = 20 days.
360 men = 8 hours per day
3 boys = 2 men
8 hours + extra an hour
=> 8 + 1
=> .
60 km , 12 km ( completed )
=> 60 - 12
=>
3 boys = 2 men ( given )
=> 1 men = 3 / 2
=>
Total men = 360
=> 360 / 1.5
=>