English, asked by sdarafath2000, 1 month ago

5. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work? O 23 O 27 040 O 371/2​

Answers

Answered by Anonymous
1

\huge\boxed{\dag\sf\red{ANSWER}\dag}

Whole \:  work  \: done \:  by \:  A\\ =20× \frac{5}{4} =25 \: days

Now

( 1 - \frac{4}{5} ) \: i.e

1/5 is work done by A and B is three days

Whole work done by B and A in

(3  \times 5)  = 15 \: days

A's 1 st day work

 =  \frac{1}{25}

A+ B 1st day work

 =  \frac{1}{15}

B' s 1 st day work

 =  \frac{1}{15}  -  \frac{1}{25}  =  \frac{4}{150} =  \frac{2}{75}

So ,B alone would do the work in

 \frac{75}{2}  = 37 \frac{1}{2}  \: days

\huge\boxed{\dag\sf\red{Thanks}\dag}

Answered by lilme0w
3

Answer:

Whole work done by A = 20 x 5/4 = 25 days

Now (1 - 4/5) i.e

1/5 is work done by and B is three days

Whole work done by B and A in (3 x 5) = 15 days

A's 1 st day work =1/25

A+B 1st day work = 1/15

B's 1st day work

= 1/15 - 1/25 = 4/150 = 2/75

So,B alone would do the work in

75/2=371/2 days