Accountancy, asked by kavita0353, 2 months ago

5. If Material Cost Variance is
Rs.50,000 (F) and Material Price
Variance Is Rs.47,500 (A) then
Material Usage variance is: *
2500 F
2500 A
52500 F
97500 F​

Answers

Answered by bhupeshkumar49
0

Answer:

2500

b/c you are genious

Answered by ravilaccs
0

Answer:

The correct answer is option A

Explanation:

Given: Material Cost Variance is Rs.50,000 (F) and Material Price

Variance Is Rs.47,500 (A)

To find: MUV

Solution:

MCV=MPV +MUV

Material cost variance has to be equal to the total of Material Price variance and Material Usage Variance

50000=47500+MUV\\MUV=50000-47500\\=2500 F