5 men and 6 boys finish a piece of work in 4 days. 4 men and 3 boys can do it in 6 days. how many days 3 men and 6 boys will be able to finish
Answers
Answered by
1
Step-by-step explanation:
let's denote Men as m and Boys as b
(5m+6b)×4=(4m+3b)×6
=>20m+24b=24m+18h
=>4m=6b ....... i
now let the number of days for 3m and 6b be x
(5m+6b)×4=(3m+6b)×x
According to i
9m×4=7m=x